FORM 6-K SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 Report of Foreign Issuer Pursuant to Rule 13a-16 or 15d-16 of the Securities Exchange Act of 1934 March 4, 2004 BRITISH ENERGY PLC (Registrant's name) 3 Redwood Crescent Peel Park East Kilbride G74 5PR Scotland (Address of principal executive offices) Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F. Form 20-F..X.. Form 40-F..... Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934. Yes ..... No ..X.. If "Yes" is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b): Exhibit Index The following document (bearing the exhibit number listed below) is furnished herewith and is made a part of this Report pursuant to the General Instructions for Form 6-K: Exhibit Description No. 1 RNS Announcement, re: February Output Statement dated 4 March, 2004 BRITISH ENERGY plc - OUTPUT STATEMENT A summary of net output from British Energy's power stations in February is given in the table below, together with comparative data for the previous financial year. 2002/03 2003/04 February Year to Date February Year to Date Output Load Output Load Output Load Output Load (TWh) Factor (%) (TWh) Factor (%) (TWh) Factor (TWh) Factor (%) (%) UK Nuclear 5.79 90 58.17 76 5.34 80 59.05 77 UK Other 0.53 41 5.23 34 1.15 85 6.94 45 Planned Outages - A refuelling outage was completed on one reactor at Hartlepool and another carried out on one reactor at Dungeness B - Low load refuelling was carried out on one reactor each at Hinkley Point B and Hunterston B. Unplanned Outages - Both reactors at Heysham 1 returned to service following the seawater cooling pipe failure outage - One reactor at Torness was shutdown as a precautionary measure for an exchange of a potentially defective fuel assembly before returning to service late February. Contact: Andrew Dowler 020 7831 3113 (Media Enquiries) Paul Heward 013552 62201 (Investor Relations) Find this News Release on our web-site: www.british-energy.com SIGNATURES Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. Date: March 4, 2004 BRITISH ENERGY PLC By:____Paul Heward____ Name: Paul Heward Title: Director - Investor Relations