Filed by Bowne Pure Compliance
United States
Securities and Exchange Commission
Washington, D.C. 20549
FORM 6-K
Report of Foreign Private Issuer
Pursuant to Rule 13a-16 or 15d-16
of the
Securities Exchange Act of 1934
For the month of
January 2009
Companhia Vale do Rio Doce
Avenida Graça Aranha, No. 26
20030-900 Rio de Janeiro, RJ, Brazil
(Address of principal executive office)
(Indicate by check mark whether the registrant files or will file annual reports under cover of
Form 20-F or Form 40-F.)
(Check One) Form 20-F þ Form 40-F o
(Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1))
(Check One) Yes o No þ
(Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7))
(Check One) Yes o No þ
(Indicate by check mark whether the registrant by furnishing the information contained in this Form
is also thereby furnishing information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.)
(Check One) Yes o No þ
(If Yes is marked, indicate below the file number assigned to the registrant in connection with
Rule 12g3-2(b). 82- .)
TABLE OF CONTENTS
Vale 2008 Production Report
ADJUSTING TO THE GLOBAL DEMAND SHOCK
Rio de Janeiro, January 21, 2009 Companhia Vale do Rio Doce (Vale) is managing its production in
accordance with the new global economic outlook emerging from the financial market stress, which
has caused a strong recessionary impact on the real economy.
In response to the ensuing significant negative shock on the global demand for minerals and metals,
Vale has acted proactively to cut back production. We have shut down the higher-cost lower-quality
output mines in our operational universe alongside other measures to fine tune our activities to
the assessment of the demand prospects in the short-term.
The numbers for iron ore production in 4Q08 showing a quarter-over-quarter decrease of 26.3% -
illustrate the effort that is being made by Vale to adjust its operational activities to the
current demand levels.
As a result of very good operational performance in previous quarters, Vale was able to achieve for
the year eight annual production records: nickel (275,400 metric tons), bauxite (11.7 million
metric tons), alumina (5.0 million metric tons), copper (311,600 metric tons), coal (4.1 million
metric tons), cobalt (2,828 metric tons), palladium (231,000 oz troy) and gold (85,000 oz troy).
FERROUS MINERALS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
IRON ORE |
|
|
80,099 |
|
|
|
85,884 |
|
|
|
63,274 |
|
|
|
303,163 |
|
|
|
301,696 |
|
|
|
-26.3 |
% |
|
|
-21.0 |
% |
|
|
-0.5 |
% |
Southeastern System |
|
|
30,743 |
|
|
|
33,186 |
|
|
|
23,066 |
|
|
|
113,781 |
|
|
|
115,428 |
|
|
|
-30.5 |
% |
|
|
-25.0 |
% |
|
|
1.4 |
% |
Itabira |
|
|
11,799 |
|
|
|
11,553 |
|
|
|
7,749 |
|
|
|
46,710 |
|
|
|
41,849 |
|
|
|
-32.9 |
% |
|
|
-34.3 |
% |
|
|
-10.4 |
% |
Mariana |
|
|
9,507 |
|
|
|
10,501 |
|
|
|
7,653 |
|
|
|
33,135 |
|
|
|
36,150 |
|
|
|
-27.1 |
% |
|
|
-19.5 |
% |
|
|
9.1 |
% |
Minas Centrais |
|
|
9,437 |
|
|
|
11,132 |
|
|
|
7,664 |
|
|
|
33,936 |
|
|
|
37,429 |
|
|
|
-31.2 |
% |
|
|
-18.8 |
% |
|
|
10.3 |
% |
Southern System |
|
|
22,598 |
|
|
|
23,025 |
|
|
|
15,599 |
|
|
|
89,337 |
|
|
|
80,461 |
|
|
|
-32.3 |
% |
|
|
-31.0 |
% |
|
|
-9.9 |
% |
MBR |
|
|
16,849 |
|
|
|
17,286 |
|
|
|
11,309 |
|
|
|
68,276 |
|
|
|
60,015 |
|
|
|
-34.6 |
% |
|
|
-32.9 |
% |
|
|
-12.1 |
% |
Minas do Oeste |
|
|
5,749 |
|
|
|
5,739 |
|
|
|
4,290 |
|
|
|
21,061 |
|
|
|
20,446 |
|
|
|
-25.2 |
% |
|
|
-25.4 |
% |
|
|
-2.9 |
% |
Carajás |
|
|
24,620 |
|
|
|
26,751 |
|
|
|
22,306 |
|
|
|
91,687 |
|
|
|
96,495 |
|
|
|
-16.6 |
% |
|
|
-9.4 |
% |
|
|
5.2 |
% |
Samarco1 |
|
|
1,870 |
|
|
|
2,633 |
|
|
|
2,060 |
|
|
|
7,231 |
|
|
|
8,322 |
|
|
|
-21.8 |
% |
|
|
10.1 |
% |
|
|
15.1 |
% |
Urucum |
|
|
267 |
|
|
|
289 |
|
|
|
244 |
|
|
|
1,128 |
|
|
|
990 |
|
|
|
-15.7 |
% |
|
|
-8.7 |
% |
|
|
-12.2 |
% |
Vales iron ore output reached 301.7 Mt in 2008, showing a slight decrease, 0.5%, relatively to
2007, when it reached 303.2 Mt 2,3. This was the first reduction in Vales annual
production of iron ore production since 1999. From 2001 to 2007 it has grown at an annual average
rate of 13.4%, as a consequence of productivity gains and large investments to increase capacity to
meet a fast growing global demand.
|
|
|
1 |
|
Production attributable to Vale |
|
2 |
|
Mt=million metric tons |
|
3 |
|
Production in 2008 was 293.4 Mt under US GAAP |
1
Given the unprecedented demand contraction across the globe resulting from a substantial cutback in
steel production, our iron ore production in the last quarter of 2008 reached 63.3 Mt, decreasing
by 26.3% relatively to 3Q08 and 21.0% against 4Q07.
The Southeastern and Southern Systems, which have been responsible for 2/3 of our iron ore
production, were responsible for 77.6% of the output reduction of 22.6 Mt in comparison to the
level reached in 3Q08.
Due to lower iron contents relatively to Carajás and the utilization of a third-party railroad
MRS to transport the production of the Southern System to two of our maritime terminals Guaíba
Island and Itaguaí costs are higher than in the Northern System, home to the highest quality iron
ore in the world.
The Southeastern System, which encompasses the Itabira, Mariana and Minas Centrais iron ore mines,
was responsible in 2008 for a record production of 115.4 Mt, contributing with 38.3% of Vales
annual production. In 4Q08 its output of 23.1 Mt was 30.5 % below the 3Q08 level.
The Southern System MBR and Minas do Oeste produced 80.5 Mt in 2008, 9.9% lower than in 2007.
The 4Q08 production decreased 32.3% relatively to 3Q08.
Carajás output reached 96.5 Mt in 2008, setting a new record, up 5.2% on the previous years
production. Given the stoppage during the year-end holidays, production was 22.3 Mt in 4Q08 versus
26.8 Mt in 3Q08.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PELLETS1 |
|
|
11,662 |
|
|
|
12,748 |
|
|
|
9,572 |
|
|
|
44,825 |
|
|
|
44,762 |
|
|
|
-24.9 |
% |
|
|
-17.9 |
% |
|
|
-0.1 |
% |
Tubarão I and II |
|
|
1,681 |
|
|
|
1,666 |
|
|
|
1,143 |
|
|
|
6,369 |
|
|
|
6,096 |
|
|
|
-31.4 |
% |
|
|
-32.0 |
% |
|
|
-4.3 |
% |
Fabrica |
|
|
1,117 |
|
|
|
1,091 |
|
|
|
965 |
|
|
|
4,148 |
|
|
|
4,165 |
|
|
|
-11.5 |
% |
|
|
-13.6 |
% |
|
|
0.4 |
% |
São Luís |
|
|
1,852 |
|
|
|
1,876 |
|
|
|
1,790 |
|
|
|
7,053 |
|
|
|
6,960 |
|
|
|
-4.6 |
% |
|
|
-3.3 |
% |
|
|
-1.3 |
% |
Nibrasco2 |
|
|
2,347 |
|
|
|
2,559 |
|
|
|
1,918 |
|
|
|
8,966 |
|
|
|
8,775 |
|
|
|
-25.1 |
% |
|
|
-18.3 |
% |
|
|
-2.1 |
% |
Kobrasco |
|
|
1,283 |
|
|
|
1,281 |
|
|
|
1,125 |
|
|
|
4,971 |
|
|
|
4,935 |
|
|
|
-12.2 |
% |
|
|
-12.3 |
% |
|
|
-0.7 |
% |
Hispanobras |
|
|
466 |
|
|
|
581 |
|
|
|
210 |
|
|
|
2,173 |
|
|
|
1,938 |
|
|
|
-63.9 |
% |
|
|
-55.0 |
% |
|
|
-10.8 |
% |
Itabrasco |
|
|
1,012 |
|
|
|
1,040 |
|
|
|
384 |
|
|
|
4,015 |
|
|
|
3,321 |
|
|
|
-63.1 |
% |
|
|
-62.0 |
% |
|
|
-17.3 |
% |
Samarco3 |
|
|
1,904 |
|
|
|
2,654 |
|
|
|
2,038 |
|
|
|
7,130 |
|
|
|
8,572 |
|
|
|
-23.2 |
% |
|
|
7.0 |
% |
|
|
20.2 |
% |
Vales attributable production of pellets, in which volumes produced by our joint ventures
Hispanobras and Samarco are computed in proportion to our stakes, reached 44.8 Mt in 2008,
approximately the same level as 2007. Vale produced 30.6 Mt of blast furnace pellets in 2008 while
direct reduction pellets output reached 14.2 Mt.
In order to deal with the global demand reduction and to avoid inventory build-up, during 4Q08 Vale
shutdown five of the seven pellet plants located at the port of Tubarão, in the state of Espirito
Santo, Brazil. In addition, two other pellet plants, São Luís, at the state of Maranhão, and
Fabrica, at the state of Minas Gerais, were shutdown in January 2009. Therefore, only two of the
nine pellet plants are currently operating.
By the same token, the start-up of operations of our new pellet plant, Itabiritos, was postponed
and our joint venture Samarco is keeping two of its three pellet plants idled since the end of
November 2008.
As a consequence of the slower pace of operational activity, our pellet production reached 9.6 Mt
in 4Q08, down 24.9% compared with 3Q08.
|
|
|
1 |
|
Production attributable to Vale on a pro forma basis.
In 2008, we entered into a leasing contract for the Nibrasco, Kobrasco and
Itabrasco pelletizing operations. As a consequence, their production is being
consolidated 100% on a pro forma basis. |
|
2 |
|
Nibrasco has two pellet plants |
|
3 |
|
Samarco has three pellet plants |
2
The Samarco contribution to our total production was 8.6 Mt in 2008, against 7.1 Mt in 2007. In
4Q08, it decreased 23.2% relatively to 3Q08.
|
|
Manganese ore and ferroalloys |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MANGANESE ORE |
|
|
118 |
|
|
|
694 |
|
|
|
491 |
|
|
|
1,333 |
|
|
|
2,383 |
|
|
|
-29.2 |
% |
|
|
316.0 |
% |
|
|
78.7 |
% |
Azul |
|
|
47 |
|
|
|
561 |
|
|
|
392 |
|
|
|
945 |
|
|
|
2,003 |
|
|
|
-30.2 |
% |
|
|
739.9 |
% |
|
|
111.8 |
% |
Urucum |
|
|
71 |
|
|
|
75 |
|
|
|
57 |
|
|
|
277 |
|
|
|
246 |
|
|
|
-23.3 |
% |
|
|
-19.8 |
% |
|
|
-11.3 |
% |
Other mines |
|
|
0 |
|
|
|
58 |
|
|
|
42 |
|
|
|
111 |
|
|
|
135 |
|
|
|
-27.9 |
% |
|
|
n.m. |
|
|
|
21.2 |
% |
|
FERROALLOY |
|
|
137 |
|
|
|
130 |
|
|
|
84 |
|
|
|
542 |
|
|
|
475 |
|
|
|
-35.5 |
% |
|
|
-38.6 |
% |
|
|
-12.4 |
% |
Brazil |
|
|
79 |
|
|
|
78 |
|
|
|
59 |
|
|
|
288 |
|
|
|
288 |
|
|
|
-24.7 |
% |
|
|
-25.7 |
% |
|
|
0.1 |
% |
Dunkerque |
|
|
16 |
|
|
|
16 |
|
|
|
0 |
|
|
|
103 |
|
|
|
55 |
|
|
|
n.a. |
|
|
|
n.a. |
|
|
|
-46.6 |
% |
Mo I Rana |
|
|
37 |
|
|
|
30 |
|
|
|
21 |
|
|
|
129 |
|
|
|
112 |
|
|
|
-29.4 |
% |
|
|
-42.1 |
% |
|
|
-13.1 |
% |
Urucum |
|
|
5 |
|
|
|
5 |
|
|
|
4 |
|
|
|
22 |
|
|
|
20 |
|
|
|
-29.7 |
% |
|
|
-28.5 |
% |
|
|
-11.3 |
% |
Production of manganese ore totaled 2.4 Mt in 2008, up 78.7% compared with 2007. The Azul mine
produced 2.0 Mt in 2008 versus 1.0 Mt in 2007, when its operations were temporarily suspended.
Our ferroalloy production in 2008 amounted to 475,000 t, lower than the level achieved in 2007, of
542,000 t. In 2008, ferroalloy production was comprised of 213,400 t of ferrosilicon manganese
alloys (FeSiMn), 209,400 t of high-carbon manganese alloys (FeMnAc) and 51,900 t of medium-carbon
manganese alloys (FeMnMC).
Our manganese ore mines and ferroalloy plants in Brazil were shut down in December 2008 and are
expected to resume operations by February 2009. The ferroalloy plant in Mo I Rana, Norway, had its
furnace maintenance extended until June 2009. Our ferroalloy operations in Dunkerque, France,
stopped in August 2008 due to problems with the electric furnace and will be kept idle until April
2009.
Due to the announced cutbacks, manganese ore production in 4Q08 was 491,000 t, compared with
694,000 t in 3Q08 and 118,000 t in 4Q07. The production of ferroalloys was reduced by 35.5% against
3Q08, reaching only 84,000 metric tons.
3
NON-FERROUS MINERALS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NICKEL1 |
|
|
69.0 |
|
|
|
72.4 |
|
|
|
73.2 |
|
|
|
247.9 |
|
|
|
275.4 |
|
|
|
1.1 |
% |
|
|
6.1 |
% |
|
|
11.1 |
% |
Sudbury |
|
|
16.9 |
|
|
|
18.4 |
|
|
|
28.8 |
|
|
|
70.7 |
|
|
|
85.3 |
|
|
|
56.6 |
% |
|
|
71.1 |
% |
|
|
20.6 |
% |
Thompson |
|
|
8.4 |
|
|
|
7.6 |
|
|
|
7.5 |
|
|
|
29.8 |
|
|
|
28.9 |
|
|
|
-1.5 |
% |
|
|
-10.4 |
% |
|
|
-3.2 |
% |
Voiseys Bay |
|
|
20.5 |
|
|
|
21.9 |
|
|
|
19.2 |
|
|
|
58.9 |
|
|
|
77.5 |
|
|
|
-12.2 |
% |
|
|
-6.3 |
% |
|
|
31.6 |
% |
Sorowako |
|
|
20.6 |
|
|
|
19.1 |
|
|
|
14.5 |
|
|
|
75.8 |
|
|
|
68.3 |
|
|
|
-23.9 |
% |
|
|
-29.2 |
% |
|
|
-9.9 |
% |
Others* |
|
|
2.7 |
|
|
|
5.4 |
|
|
|
3.1 |
|
|
|
12.7 |
|
|
|
15.4 |
|
|
|
-43.2 |
% |
|
|
14.5 |
% |
|
|
21.0 |
% |
|
|
|
* |
|
External feed purchased from third parties and processed into finished nickel in our
operations. |
Our finished nickel production reached an all-time high in 2008, at 275,400 t, rising 11.1%
relatively to 2007. This performance highlights the ongoing improvement in asset performance, a
consequence of our efforts to upgrade existing facilities.
The volume produced in 4Q08 73,200 t increased 1.1% compared to 3Q08, as Sudbury showed a
strong increase in production in 4Q08.
Finished nickel originated from Sudbury, located in the Canadian province of Ontario, was 85,300 t
in 2008, 14,600 t higher than the level reached in 2007, as a result of strong operational
performance at the mines, mill, smelter complex and refineries. The increase in Sudbury source
output came simultaneously with a rising production of finished nickel pellets and powders from
both the Copper Cliff Nickel Refinery, at Sudbury, and the Clydach
Refinery
2, in Wales, UK, and
decreased sinter production.
The higher proportion of pellet and powder production was also reflective of availability and high
feed quality from matte processing, and excellent operating performance at both refineries, which
was due largely to capital investment in new equipment.
Production at Thompson, in the province of Manitoba, was 28,900 t in 2008. In 4Q08, it decreased
1.5% over 4Q07.
Voiseys Bay nickel-in-concentrate production in 2008 was 77,500 t, which was 18,600 t higher than
2007. This is due to continuing above-plan ore grades and good asset performance. In 4Q08 its
production was 19,200 t, being 2,700 t below 3Q08.
Nickel-in-matte output from our Indonesian operations at Sorowako amounted to 68,300 t in 2008,
below the 75,800 t reached last year. The production of Sorowako was 14,500 t in 4Q08, 6,100 t
below that of 4Q07 and 4,600 t below 3Q08. This was primarily due to the decision to reduce
production to adjust to the lower demand for utility nickel arising from the sharp decrease in
global stainless steel output. We have decided to shut down production fed by thermal power
generation and rely solely on less expensive hydroelectric power generated by our Larona and
Balambano plants. This is an important measure given the energy intensiveness of saprolitic nickel
processing.
|
|
|
1 |
|
The figures shown for finished nickel production do not
include the quantities produced from nickel concentrates purchased from other
companies and processed externally under tolling arrangements. These volumes
were 14,200 t in 2007 and 7,500 t in 2008. |
|
2 |
|
Clydach refines part of the Sudbury feed.
|
|
|
|
Figures for our operations at Sudbury and Thompson include only the
production from feed originating from our own mines. It excludes any
concentrates purchased from third parties, which are subsequently processed in
our operations. |
4
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
BAUXITE |
|
|
2,668 |
|
|
|
3,198 |
|
|
|
3,541 |
|
|
|
9,114 |
|
|
|
11,628 |
|
|
|
10.7 |
% |
|
|
32.7 |
% |
|
|
27.6 |
% |
Trombetas1 |
|
|
1,850 |
|
|
|
1,883 |
|
|
|
1,980 |
|
|
|
7,223 |
|
|
|
7,225 |
|
|
|
5.2 |
% |
|
|
7.1 |
% |
|
|
0.0 |
% |
Paragominas |
|
|
819 |
|
|
|
1,316 |
|
|
|
1,561 |
|
|
|
1,890 |
|
|
|
4,403 |
|
|
|
18.6 |
% |
|
|
90.6 |
% |
|
|
132.9 |
% |
In 2008, bauxite production hit an all-time high of 11.6 Mt, 27.6% above the previous record of 9.1
Mt.
In 4Q08 it reached a new record of 3.5 Mt, an increase of 32.7% compared with 2.7 Mt in 4Q07,
primarily as a result of the Paragominas ramp up. Vale`s attributable production at Trombetas also
set a new record, of 2.0 Mt.
The Paragominas bauxite mine, in the Brazilian state of Pará, produced 4.4 Mt in 2008, as its first
expansion Paragominas II began ramping up in May 2008, adding 4.5 Mtpy to the total nominal
capacity.
The Paragominas mine is linked to the Alunorte alumina refinery by the first bauxite pipeline in
the world. Since the onset of the operations the bauxite produced has had smaller granules than
planned, causing lower than expected performance. To eliminate this problem additional filters were
ordered. This will allow us to run Paragominas at its capacity of 9.9 Mt from 1H10 onwards.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ALUMINA |
|
|
1,158 |
|
|
|
1,309 |
|
|
|
1,597 |
|
|
|
4,253 |
|
|
|
5,028 |
|
|
|
22.0 |
% |
|
|
38.0 |
% |
|
|
18.2 |
% |
Alunorte |
|
|
1,158 |
|
|
|
1,309 |
|
|
|
1,597 |
|
|
|
4,253 |
|
|
|
5,028 |
|
|
|
22.0 |
% |
|
|
38.0 |
% |
|
|
18.2 |
% |
Vale produced 5.0 Mt of alumina in 2008, up 18.2% against 2007, setting a new record figure.
Stages 6 and 7 of the Barcarena refinery started ramping up in June and July 2008, respectively,
augmenting its nominal capacity to 6.26 million metric tons per year.
The volume produced in 4Q08 reached 1.6 Mt as against 1.2 Mt in 4Q07 and 1.3 Mt in 3Q08.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ALUMINUM |
|
|
139 |
|
|
|
140 |
|
|
|
135 |
|
|
|
551 |
|
|
|
543 |
|
|
|
-3.2 |
% |
|
|
-2.5 |
% |
|
|
-1.5 |
% |
Albras |
|
|
114 |
|
|
|
115 |
|
|
|
115 |
|
|
|
455 |
|
|
|
455 |
|
|
|
-0.2 |
% |
|
|
0.8 |
% |
|
|
0.0 |
% |
Valesul |
|
|
25 |
|
|
|
25 |
|
|
|
20 |
|
|
|
95 |
|
|
|
87 |
|
|
|
-17.1 |
% |
|
|
-17.5 |
% |
|
|
-8.5 |
% |
Our production of aluminum was 543,000 t in 2008 versus 551,000 t in 2007, due to an 8,000 t
shortfall at the Valesul smelter.
|
|
|
1 |
|
Production attributable to Vale |
5
In 4Q08, production reached 135,000 t against 140,000 t in the previous quarter. The production of
Albras remained constant at 115,000 t while it was reduced by 5,000 t at Valesul.
In line with our strategic decision to implement larger production cutbacks at higher cost units,
Valesul production will be temporarily limited to 40% of its nominal annual capacity of 95,000 t,
to comply with contractual obligations.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COPPER |
|
|
74.3 |
|
|
|
80.2 |
|
|
|
81.6 |
|
|
|
284.4 |
|
|
|
311.6 |
|
|
|
1.8 |
% |
|
|
9.9 |
% |
|
|
9.6 |
% |
Sossego |
|
|
32.0 |
|
|
|
32.8 |
|
|
|
32.6 |
|
|
|
118.0 |
|
|
|
125.9 |
|
|
|
-0.7 |
% |
|
|
1.9 |
% |
|
|
6.7 |
% |
Sudbury |
|
|
29.2 |
|
|
|
30.8 |
|
|
|
28.0 |
|
|
|
113.2 |
|
|
|
115.3 |
|
|
|
-8.9 |
% |
|
|
-4.1 |
% |
|
|
1.9 |
% |
Thompson |
|
|
0.3 |
|
|
|
0.3 |
|
|
|
0.3 |
|
|
|
1.3 |
|
|
|
1.4 |
|
|
|
-14.0 |
% |
|
|
-16.0 |
% |
|
|
7.1 |
% |
Voiseys Bay |
|
|
10.5 |
|
|
|
13.2 |
|
|
|
16.1 |
|
|
|
42.3 |
|
|
|
55.4 |
|
|
|
21.9 |
% |
|
|
53.8 |
% |
|
|
31.1 |
% |
Others |
|
|
2.0 |
|
|
|
3.0 |
|
|
|
4.6 |
|
|
|
9.4 |
|
|
|
13.5 |
|
|
|
51.7 |
% |
|
|
135.6 |
% |
|
|
43.7 |
% |
Vales copper production totaled 311,600 t in 2008 setting a new record and increasing by 9.6%
relatively to 2007.
Copper-in-concentrate production at Sossego, Carajás, was 125,900 t in 2008, increasing 6.7%
against 118,000 t in 2007 when there was a maintenance stoppage at the processing plant in 3Q07.
The Canadian operations, where copper is produced as a by-product of nickel, were responsible for
172,100 t, equal to 55.2% of our total production in 2008. This meant an increase of 15,300 t over
2007, primarily driven by higher copper grades at Voiseys Bay.
Production in 4Q08 reached 81,600 t, with a 1.8% increase over 3Q08.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
|
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COBALT (metric tons) |
|
|
680 |
|
|
|
750 |
|
|
|
792 |
|
|
|
2,524 |
|
|
|
2,828 |
|
|
|
5.6 |
% |
|
|
16.4 |
% |
|
|
12.1 |
% |
Sudbury |
|
|
127 |
|
|
|
210 |
|
|
|
294 |
|
|
|
727 |
|
|
|
804 |
|
|
|
40.1 |
% |
|
|
132.0 |
% |
|
|
10.6 |
% |
Thompson |
|
|
47 |
|
|
|
44 |
|
|
|
22 |
|
|
|
179 |
|
|
|
168 |
|
|
|
-49.5 |
% |
|
|
-52.7 |
% |
|
|
-6.4 |
% |
Voiseys Bay |
|
|
430 |
|
|
|
447 |
|
|
|
469 |
|
|
|
1,239 |
|
|
|
1,695 |
|
|
|
4.9 |
% |
|
|
8.9 |
% |
|
|
36.8 |
% |
Others |
|
|
77 |
|
|
|
50 |
|
|
|
8 |
|
|
|
379 |
|
|
|
161 |
|
|
|
-84.7 |
% |
|
|
-90.0 |
% |
|
|
-57.5 |
% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PLATINUM (000oz troy) |
|
|
29 |
|
|
|
44 |
|
|
|
43 |
|
|
|
140 |
|
|
|
166 |
|
|
|
-2.1 |
% |
|
|
49.0 |
% |
|
|
19.1 |
% |
Sudbury |
|
|
29 |
|
|
|
44 |
|
|
|
43 |
|
|
|
140 |
|
|
|
166 |
|
|
|
-2.1 |
% |
|
|
49.0 |
% |
|
|
19.1 |
% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PALLADIUM (000oz troy) |
|
|
40 |
|
|
|
66 |
|
|
|
62 |
|
|
|
191 |
|
|
|
231 |
|
|
|
-6.1 |
% |
|
|
57.8 |
% |
|
|
20.8 |
% |
Sudbury |
|
|
40 |
|
|
|
66 |
|
|
|
62 |
|
|
|
191 |
|
|
|
231 |
|
|
|
-6.1 |
% |
|
|
57.8 |
% |
|
|
20.8 |
% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
GOLD (000 oz troy) |
|
|
14 |
|
|
|
24 |
|
|
|
21 |
|
|
|
75 |
|
|
|
85 |
|
|
|
-13.7 |
% |
|
|
43.8 |
% |
|
|
13.7 |
% |
Sudbury |
|
|
14 |
|
|
|
24 |
|
|
|
21 |
|
|
|
75 |
|
|
|
85 |
|
|
|
-13.7 |
% |
|
|
43.8 |
% |
|
|
13.7 |
% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
SILVER (000 oz troy) |
|
|
522 |
|
|
|
650 |
|
|
|
574 |
|
|
|
2,199 |
|
|
|
2,308 |
|
|
|
-11.6 |
% |
|
|
9.9 |
% |
|
|
5.0 |
% |
Sudbury |
|
|
522 |
|
|
|
650 |
|
|
|
574 |
|
|
|
2,199 |
|
|
|
2,308 |
|
|
|
-11.6 |
% |
|
|
9.9 |
% |
|
|
5.0 |
% |
6
The production for all nickel by-products increased in 2008 relatively to 2007.
In 2008, cobalt production reached a record of 2,828 t, with a 12.1% increase relative to last
year, driven by the good performance of Voisey`s Bay. Cobalt production in 4Q08 was 792 t, 5.6%
above 3Q08 and 16.4% higher than 4Q07. This is due to improved recoveries through Sudbury and
continuing higher ore grades at Voiseys Bay.
Platinum and palladium outputs increased by 19.1% and 20.8%, respectively, in 2008. Production of
PGMs and precious metals for 4Q08 was above 4Q07.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
POTASH |
|
|
173 |
|
|
|
172 |
|
|
|
102 |
|
|
|
671 |
|
|
|
607 |
|
|
|
-40.9 |
% |
|
|
-41.3 |
% |
|
|
-9.6 |
% |
Taquari-Vassouras |
|
|
173 |
|
|
|
172 |
|
|
|
102 |
|
|
|
671 |
|
|
|
607 |
|
|
|
-40.9 |
% |
|
|
-41.3 |
% |
|
|
-9.6 |
% |
Annual production at Taquari-Vassouras reached 607,000 t in 2008, showing a decrease of 9.6%
compared to the previous year.
Our potash operations were temporarily shut down in November 2008, following the slump in global
demand. This resulted in a sharp reduction in the 4Q08 output, 40.9% against 3Q08, amounting to
102,000 t.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
2007 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
KAOLIN |
|
|
379 |
|
|
|
314 |
|
|
|
231 |
|
|
|
1,354 |
|
|
|
1,129 |
|
|
|
-26.4 |
% |
|
|
-39.1 |
% |
|
|
-16.6 |
% |
PPSA |
|
|
185 |
|
|
|
136 |
|
|
|
99 |
|
|
|
639 |
|
|
|
528 |
|
|
|
-27.1 |
% |
|
|
-46.5 |
% |
|
|
-17.5 |
% |
Cadam |
|
|
194 |
|
|
|
178 |
|
|
|
132 |
|
|
|
714 |
|
|
|
602 |
|
|
|
-25.8 |
% |
|
|
-32.0 |
% |
|
|
-15.8 |
% |
In 2008, Vale`s production of kaolin reached 1.1 Mt, below the 2007 figure of 1.4 Mt. At PPSA,
528,000 t were produced in 2008, decreasing 17.5% against 2007, while at Cadam the production was
602,000 t, down 15.8%.
The slowdown of kaolin demand for paper coating led us to cut back production by 30% at both of our
subsidiaries, Cadam and PPSA. Production for 4Q08 amounted to 231,000 t, down 39.1% versus 4Q07 and
26.4% against 3Q08.
7
COAL
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
% change |
|
|
% change |
|
|
% change |
|
000 metric tons |
|
4Q07 |
|
|
3Q08 |
|
|
4Q08 |
|
|
20071 |
|
|
2008 |
|
|
4Q08/3Q08 |
|
|
4Q08/4Q07 |
|
|
2008/2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
METALLURGICAL COAL |
|
|
758 |
|
|
|
686 |
|
|
|
703 |
|
|
|
1,764 |
|
|
|
2,808 |
|
|
|
2.4 |
% |
|
|
-7.2 |
% |
|
|
59.2 |
% |
Integra Coal |
|
|
548 |
|
|
|
448 |
|
|
|
441 |
|
|
|
1,214 |
|
|
|
1,747 |
|
|
|
-1.6 |
% |
|
|
-19.6 |
% |
|
|
43.9 |
% |
Carborough Downs |
|
|
101 |
|
|
|
76 |
|
|
|
126 |
|
|
|
269 |
|
|
|
429 |
|
|
|
66.1 |
% |
|
|
24.0 |
% |
|
|
59.6 |
% |
Broadlea |
|
|
5 |
|
|
|
60 |
|
|
|
45 |
|
|
|
32 |
|
|
|
249 |
|
|
|
-25.8 |
% |
|
|
n.m. |
|
|
|
n.m. |
|
Other |
|
|
103 |
|
|
|
103 |
|
|
|
92 |
|
|
|
249 |
|
|
|
382 |
|
|
|
-10.3 |
% |
|
|
-10.3 |
% |
|
|
53.5 |
% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
THERMAL COAL |
|
|
220 |
|
|
|
362 |
|
|
|
387 |
|
|
|
440 |
|
|
|
1,286 |
|
|
|
7.1 |
% |
|
|
75.6 |
% |
|
|
192.1 |
% |
Integra Coal |
|
|
118 |
|
|
|
116 |
|
|
|
184 |
|
|
|
255 |
|
|
|
557 |
|
|
|
58.2 |
% |
|
|
55.5 |
% |
|
|
118.2 |
% |
Broadlea |
|
|
2 |
|
|
|
209 |
|
|
|
150 |
|
|
|
14 |
|
|
|
582 |
|
|
|
-28.0 |
% |
|
|
n.m. |
|
|
|
n.m. |
|
Other |
|
|
100 |
|
|
|
37 |
|
|
|
53 |
|
|
|
171 |
|
|
|
147 |
|
|
|
44.7 |
% |
|
|
-47.1 |
% |
|
|
-13.7 |
% |
|
|
|
1 |
|
May to December 2007
figures. |
Coal production was 4.1 Mt in 2008, comprised of 2.8 Mt of metallurgical coal and 1.3 Mt of thermal
coal. Total coal production in 4Q08 reached a record of 1.1 Mt, 703,000 t of which is metallurgical
coal and 387,000 t thermal coal.
Most of our coal production 57.3% of Vales total comes from Integra Coal in the Hunter Valley,
state of New South Wales, Australia, where the production in 4Q08 was impacted by problems on feed
rate, overall utilization of the coal handling preparation plant (CHPP) and the wet weather in
December.
Production of coal at Carborough Downs totaled 126,000 t in 4Q08, as a result of an improvement in
its performance.
The joint production of Broadlea and Carborough Downs is transported through the Goonyella logistic
corridor, connecting the mines of Central Queensland Bowen Basin to the Dalrymple Bay coal
terminal. Broadlea produced a total of 195,000 t during 4Q08, which was impacted by low performance
of the CHPP, shared by the two mines.
8
For further information, please contact:
+55-21-3814-4540
Roberto Castello Branco: roberto.castello.branco@vale.com
Alessandra Gadelha: alessandra.gadelha@vale.com
Marcus Thieme: marcus.thieme@vale.com
Patrícia Calazans: patrícia.calazans@vale.com
Roberta Coutinho: roberta.coutinho@vale.com
Theo Penedo: theo.penedo@vale.com
Tacio Neto: tacio.neto@vale.com
This press release may include declarations that present Vales expectations in relation to future
events or results. All declarations, when based upon future expectations and not on historical
facts involve various risks and uncertainties. Vale cannot guarantee that such declarations will
come to be correct. These risks and uncertainties include factors related to the following: (a)
countries where we operate, mainly Brazil and Canada; (b) global economy; (c) capital markets; (d)
iron ore and nickel businesses and their dependence upon the global steel industry, which is
cyclical by nature; (e) factors of high degree of global competition in the markets which Vale
operates. To obtain further information on factors that may give origin to results different from
those forecasted by Vale, please consult the reports filed with the Brazilian Securities and
Exchange Commission (CVM), the Autorité des Marchés Financiers (AMF), and with the U.S. Securities
and Exchange Commission (SEC), including the most recent Annual Report Vale Form 20F and 6K
forms.
9
Signatures
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
|
|
|
|
|
|
COMPANHIA VALE DO RIO DOCE
(Registrant)
|
|
Date: January 21, 2009 |
By: |
/s/ Roberto Castello Branco
|
|
|
|
Roberto Castello Branco |
|
|
|
Director of Investor Relations |
|
|